London Timing #245

Closed
Closed
@timbeiko

Description

@timbeiko

Given that the difficulty bomb is expected to go off sometime in July, we will want London to hit mainnet then.

If we want a reasonable delay between picking blocks, going live on testnets, and going live on mainnet, this means we need to roughly follow the following timeline:

  • July: Mainnet
  • June: Testnets
  • May: Blocks chosen, London testing done
  • April: Select final EIPs + Reference Testing + Wrap up ephemeral network testing
  • March: Select initial EIPs + Start ephemeral network testing

In other words, given we are already late-February, we should start thinking about what we want to see included in the London YOLO-nets (along with the difficulty bomb pushback (see EIP-3238)) if we want to not be rushed in implementation and deployment. This will be a bit of a change from our current process, as we'll need to start working on London before Berlin is live.

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions