Given that the difficulty bomb is expected to go off sometime in July, we will want London to hit mainnet then.
If we want a reasonable delay between picking blocks, going live on testnets, and going live on mainnet, this means we need to roughly follow the following timeline:
- July: Mainnet
- June: Testnets
- May: Blocks chosen, London testing done
- April: Select final EIPs + Reference Testing + Wrap up ephemeral network testing
- March: Select initial EIPs + Start ephemeral network testing
In other words, given we are already late-February, we should start thinking about what we want to see included in the London YOLO-nets (along with the difficulty bomb pushback (see EIP-3238)) if we want to not be rushed in implementation and deployment. This will be a bit of a change from our current process, as we'll need to start working on London before Berlin is live.